Sassals Windows, Wollongong |
|
| |
Date of Commencement:
Date of Completion:
|
February 08
April 08 |
|
|
| |
Scope:
Bonded Asbestos removal and full demolition of approximately 30,000m² of concrete ground slab. The project also required the careful removal of iron cladding for the re-erection of pre cast concrete and tilt up panels.
The project was completed well within our programmed time and on budget and incident free. The job also included close liaison with Rail Corp, with the training and employment of specialty services for the demolition of one of the structures which encroached onto Rail territory. This demolition was a great success with no inconvenience to rail commuters. |
|
| |
|
|
| |
|
|
| |
|
|
|
| |
|
|